A building can look finished, the contractor can have reached practical completion and the site team may be preparing to leave. But for some new residential developments in London, there is another hurdle before a higher-risk building can receive its completion certificate: confirmation that the Building Safety Levy has been paid, or that a valid notice of no charge applies.
That creates a handover issue with a practical insurance consequence. There may be a period when the works are complete, but the building cannot yet be handed over or occupied. The insurance arranged for construction and the cover intended for an operating, occupied property may not line up automatically.
This is not a repeat of the earlier Gateway 2 approval question. The concern here is the later completion stage, and what developers and contractors should do about the interval between practical completion and permission to move forward.
1. There are two different meanings of “finished”
Practical completion is a milestone under the building contract. What it means, and what follows from it, depends on that contract. It may trigger payment, transfer responsibility for parts of the site, or start a defects period.
A Gateway 3 completion certificate is different. For higher-risk building work, it is part of the Building Safety Regulator’s completion process. Building registration and the requirements for occupation are separate steps again. Reaching practical completion does not, by itself, mean those statutory requirements have been met.

The difference matters because the contractor’s delivery milestone and the developer’s ability to hand units over may fall on different dates. A contractor may have completed its work and left site, while the developer is still waiting for the completion certificate or another required step before occupation.
I think project programmes should now show these milestones separately, rather than treating practical completion as a reliable proxy for the whole handover. Contract terms, payment dates and responsibilities during any interval should be clear about which milestone they refer to.
2. A third-party confirmation can affect the critical path
The levy applies to qualifying building control applications made on or after 1 October 2026, subject to the regulations’ charging conditions and exemptions. It generally concerns major residential development of at least 10 new dwellings or 30 purpose-built student accommodation bedspaces. Gateway 3 has a different scope: it is the BSR’s completion certificate process for higher-risk building work.
For relevant higher-risk building applications, the completion application must include a levy liability statement. The named client must also provide the relevant information to the collecting authority. Under regulation 63 of the Building Safety Levy (England) Regulations 2025, the collecting authority must tell the regulator within 10 working days whether it agrees with the statement.
Where levy requirements apply, the BSR cannot issue the completion certificate until the required levy position is confirmed: payment in full, or a valid notice of no charge. That confirmation sits outside the BSR’s technical assessment. A building can therefore be ready from a construction point of view while a separate administrative step remains outstanding.
The levy process itself also needs time. The collecting authority normally has five weeks after receiving sufficient information to issue a liability notice or a notice of no charge; a spot-check can extend that route to eight weeks. Once the levy has been paid in full, the payment certificate is due within two weeks. The levy is payable by the earlier of the relevant completion notice date or first occupation under regulation 24.

Recent figures underline why it is worth planning this carefully, while they should not be mistaken for proof that every project is stuck at Gateway 3. The BSR’s performance dataset, published on 6 November and corrected on 11 November, recorded no new-build project that had passed Gateway 2 as having reached Gateway 3 by 1 November 2026. It showed applications in progress for internal works and remediation, but none for new higher-risk buildings and conversions. The BSR dataset provides the latest published picture.
The numbers do not tell us why any individual handover is delayed. But they do show that new-build Gateway 3 completions had not yet begun to appear in the published data by that date. Teams should not assume the levy confirmation will be a quick final signature.
3. Check the insurance dates before practical completion
The interval between practical completion and occupation can create an insurance question. Contract works cover may end at practical completion, handover, occupation or another event specified by the policy. Property and business interruption arrangements for a completed building may also depend on how the property is used, whether it is occupied and when cover starts.
There is no single rule that means every project will have an uninsured gap. The risk is that the policy dates and conditions do not match what actually happens on the project. A finished but not-yet-occupiable building may be subject to unoccupied-property conditions, for example, and some policies set requirements or limits after a stated period. The wording and time limits vary.

Before practical completion, tell your insurer or broker in writing the expected practical completion date, the likely Gateway 3 certificate date and when occupation is expected to begin. Ask them to confirm which policy covers the building during the intervening period, what conditions apply, and whether the end date for works cover matches the start date for property cover.
It is also worth checking what happens if the certificate takes longer than expected. A short extension agreed in advance may be easier to arrange than trying to resolve a coverage question after a delay has already occurred.
4. Levy figures vary by borough, and project values need checking
Levy rates are not uniform across London. As an illustration, 10,000 square metres of chargeable floorspace at standard rates would produce a levy of ÂŁ1,003,500 in Kensington and Chelsea, compared with ÂŁ424,700 in Barking and Dagenham. That is a difference of ÂŁ578,800 for the same assumed floorspace. These figures assume all the floorspace is chargeable, one borough rate applies and no exemptions reduce the amount.
The previously developed land rate is lower, but eligibility depends on the site meeting the rules. At least 75% of the land within the planning red-line boundary must qualify, and the 2026 amendments changed parts of the definition. That makes good site evidence important.
The point here is not to revisit the general cost or viability debate. It is that the settled levy position should be reflected accurately in the project’s financial and insurance information. If contract sums, declared values or other insured figures were set before the levy position was known, check whether they need updating. Under-declaring relevant values can become a claims issue, not just an administrative oversight.
For a closer look at construction cover, see our guide to Construction Contractor Insurance. Developers and contractors can also review General Contractor Liability Insurance and the options available under Commercial Combined Insurance.
5. Check transition dates and partial completion plans early
A qualifying application properly made before 1 October 2026 is generally outside the new levy regime, including certain variations and commencement notices. But if an application is rejected and a fresh one has to be submitted on or after that date, the new regime may apply. The exact position depends on the application and its history, so confirm it with the relevant collecting authority and your legal adviser rather than relying on an assumed project start date.
Phased work needs similar care. A partial completion certificate requires an approved strategy; splitting the construction into phases does not automatically defer an unpaid levy charge. Under the regulations, the levy due date for higher-risk building work can be linked to the relevant completion certificate or partial completion certificate application, or to first occupation, whichever comes earlier.
Practical next steps
For projects approaching completion, put the key dates and responsibilities on one page: practical completion, the Gateway 3 application, levy notification and confirmation, certificate, registration steps, and planned occupation. Confirm who is responsible for each action and allow time for the collecting authority’s process.
Then ask your broker to review the policy dates and conditions against that timeline. In particular, check the end of contract works cover, the start of property cover, any unoccupied-property requirements, and the insured values. For contractors seeking Business Insurance Essex or Business Insurance London, the same principle applies: make sure the cover reflects the project as it will actually operate, not simply the date the site team expects to finish.
The useful question is not just “When will the works be complete?” It is “What cover applies until the building is certified, registered where required and ready for occupation?” A clear answer before practical completion can help avoid a difficult conversation after handover plans have already slipped.