A Bridge Struck Every Five Hours: What 1,706 Railway Bridge Strikes Mean for Contractors’ Deliveries

A contractor does not have to own a lorry to carry transport risk. If your business arranges a scaffold wagon, a hiab delivery, a tipper for muck-away or a low loader carrying an excavator, the route and the way the load gets to site can affect your programme, your contracts and your insurance.

The latest figures make the scale hard to ignore. Network Rail recorded 1,706 railway bridge strikes in 2025/26, from 1 April 2025 to 31 March 2026. That was 40 more than the previous year, and works out at about one strike every five hours. The incidents caused 185,319 minutes of passenger delay and cost about £13.25 million in delays, cancellations and repairs, according to Network Rail’s figures reported by Rail Construction Today.

For contractors, the point is not that every delivery journey is about to go wrong. It is that transport is often treated as a supplier’s problem, even when the consequences of a failed or delayed delivery land on the site team. I think it deserves to be part of the job planning and insurance conversation.

1. The bill is rarely just the bridge

A railway bridge may need repair after a strike, but the direct repair cost is only part of the picture. Network Rail says the bridge must be examined after every incident to confirm it is safe, and debris has to be cleared. The resulting inspection, rail delays and cancellations can make the wider bill much larger than the visible damage.

Network Rail operates 30,000 bridges, tunnels and viaducts across 20,000 miles of track. Its infrastructure director, Simon Pumphrey, said each strike has the potential to cause significant disruption while engineers carry out essential safety checks.

That matters when you read your liability policy. Ask what cover responds to third-party property damage, and whether consequential delay costs are included, excluded or subject to specific terms. Do not assume that a policy which covers damage to someone else’s property will automatically deal with every financial consequence of a bridge strike. The answer depends on the wording, the circumstances and who is legally responsible.

This is one reason Construction Contractor Insurance should be reviewed against the way the business actually operates, not just the trade description on the schedule. A general contractor insurance broker can help you understand how liability cover fits alongside your contracts and delivery arrangements.

2. Height checks belong in procurement, not just in the cab

Network Rail’s research found that 43% of lorry drivers admit to not measuring their vehicle before setting off, 32% set off without knowing their vehicle height, and 56% did not consider low bridges when planning a journey. Most vehicles involved in bridge strikes are HGVs and buses.

That should prompt a practical question for contractors: if you arrange transport through a supplier or subcontractor, when do you confirm that the vehicle and load are suitable for the route? A conversation at 6am, after the lorry is loaded and on its way, is late in the process.

For a scaffold wagon, open trailer or low loader, the relevant height is the vehicle as it is actually travelling, including the load and its configuration. Agree in advance who confirms that information, who plans the route and what happens if the proposed vehicle cannot safely reach the site. Keep the answer in the delivery instructions rather than relying on assumptions or an informal phone call.

Hand-drawn sketch of a delivery driver using an orange tape measure to check the height of a loaded trailer

Network Rail’s Wise Up, Size Up campaign offers guidance for drivers and logistics businesses. For contractors, the useful takeaway is simple: ask about vehicle height before dispatch, and make sure that check is part of your procurement process when someone else is providing the haulage.

3. The route to site is part of the method statement

A load can be correctly ordered and still fail to arrive if the route is not suitable. Low bridges, weight limits and width restrictions may require a diversion, a different vehicle, transhipment or cancellation. In each case, the site may be waiting for plant or materials while the programme continues to move.

Walk or check the delivery route before the first load, especially where access is tight or the site is in a built-up area. Put known constraints in writing to the supplier and keep a record of what was agreed. For repeat deliveries, make sure route instructions are current and still apply to the vehicle being sent.

This is particularly relevant across Essex, Kent and London, where a straightforward-looking final approach can involve restrictions that are not obvious from the site entrance. A foreman’s access notes should cover more than the gate width and unloading point: record the route constraints and who is responsible for checking them.

Hand-drawn sketch of a site foreman checking a route map with low bridges marked in orange and a delivery van behind

A delivery that does not arrive is a programme issue, but it can also become a contractual argument. Clear instructions and a documented plan will not prevent every delay, but they make it easier to establish what was arranged and where responsibility sits.

4. Understand how costs and claims may come back to you

Network Rail says it can seek to recover costs from hauliers following legal cases, although some bridge strikes are hit and run. If a subcontractor or haulier you arranged causes a strike, a claim or a dispute may reach your business through the contract, depending on the facts and the wording.

Check the indemnity and delivery clauses in your agreements. Be clear about who arranges the transport, who is responsible for route planning, and what evidence is required if there is an incident. Do not rely on a broad assumption that “the haulier is responsible” without checking the actual terms.

Tell your broker if you provide transport or arrange it as part of your work, rather than simply receiving goods at the site. Your insurance arrangements should reflect the activities you carry out and the contractual responsibilities you accept. General Contractor Liability Insurance is not a substitute for reviewing those responsibilities, and no single policy should be assumed to cover every loss arising from a transport incident.

5. Plant movements bring height, weight and property exposures together

A low loader carrying an excavator is an obvious example, but the same planning issue can arise with hiab deliveries, scaffold wagons and mobile plant. These journeys can involve height, weight, route and third-party property risks at the same time.

Record driver competence and licence checks, and confirm that the person planning a journey has the information needed to select a suitable vehicle and route. Check the limits and terms for goods in transit and hired-in plant, and tell your insurer what your business actually moves. If the work or transport arrangements have changed since renewal, raise that before there is a claim to deal with.

A commercial combined policy may bring together several areas of business cover, but the detail matters: check the insured activities, limits, exclusions and any conditions against your own operations. For businesses looking at Business Insurance Essex or Business Insurance London, a broker should understand both the work you do and the way equipment and materials get to site.

Network Rail has trialled cameras and sensors at Harlaxton Road bridge in Grantham with BES Group. During the trial, the system detected strikes and supplied information that could support quicker assessment on most, but not all, occasions; Network Rail says it is refining the technology. That may help engineers assess incidents, but it does not replace careful planning by the businesses whose vehicles use the roads.

Practical next steps

Before your next delivery, identify who is confirming the vehicle height, load dimensions and route. Put restrictions in writing, check the relevant contract clauses and ask your broker to review whether your liability, goods in transit and hired-in plant arrangements match the work you actually undertake.

A bridge strike can disrupt far more than a single journey. Contractors who treat transport as part of the job plan, rather than something that starts at the site gate, are in a better position to avoid preventable delays and understand where the financial responsibilities sit.